While the DEEP DRILLER is loaded as shown in Sample Form #4 (Drilling), casing is accidentally dropped over the port side. Because the sounding level and port aft inclination are slowly increasing, you decide that tank 10P has minor damage. Among the possible corrective actions is __________.

  1. Adeballast from tank 9P ✓
  2. Bdump the mud
  3. Ccounterflood into 2S
  4. Dcounterflood into 10P

Correct answer: A) deballast from tank 9P

USCG question bank (2008) · Deck Safety – Question Bank Book 4 · pass mark 70%