While the DEEP DRILLER is loaded as shown in Sample Form #4 (Drilling), casing is accidentally dropped over the port side. Because the tank sounding level and port forward inclination are rapidly increasing, you decide that tank 1P is damaged. Your best countermeasure is to __________.
- Adeballast from tank 2P ✓
- Bdump the mud
- Ccounterflood into 9S
- Dcounterflood into C3S
Correct answer: A) deballast from tank 2P