Which procedure should be followed to dry out the fireside of a boiler after water washing?

  1. APlace trays of silica gel in the furnace.
  2. BAlternately fire one burner for 15 minute intervals during a 5 hour period. ✓
  3. COpen the furnace registers and run the forced draft fans for 3 hours.
  4. DUse a wire reinforced steam hose to put superheated steam in the furnace for 6 hours.

Correct answer: B) Alternately fire one burner for 15 minute intervals during a 5 hour period.

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%