In the absence of the manufacturer's instructions, a good procedure in reassembling a high pressure boiler gage glass is to tighten the nuts in pairs and __________.

  1. Abegin with the center bolts and work toward the ends ✓
  2. Bbegin with the end bolts and work toward the center
  3. Cstart at the top and work down
  4. Dstart at the bottom and work up

Correct answer: A) begin with the center bolts and work toward the ends

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%