A water-tube boiler can be laid up either wet or dry. If it is to be laid up wet, you should __________.

  1. Acompletely fill the boiler with water, then blow down to steaming level
  2. Bcompletely fill the boiler with deaerated feed water and maintain a slight pressure ✓
  3. Cdrain and refill the boiler each week
  4. Ddrain and refill the boiler when the pH goes above 6

Correct answer: B) completely fill the boiler with deaerated feed water and maintain a slight pressure

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%