Which of the listed actions should be carried out if a ship is to be laid up for an indefinite period of time?

  1. ABoilers to be laid up wet should be completely filled. ✓
  2. BAll fuel tanks should be cleaned and gas freed.
  3. CAll potable water tanks should be cleaned and disinfected.
  4. DAll of the above.

Correct answer: A) Boilers to be laid up wet should be completely filled.