All electric cables passing through watertight bulkheads must be __________.

  1. Ainstalled with watertight stuffing tubes ✓
  2. Bgrounded on both sides of the bulkhead
  3. Cfitted with unions on each side of the bulkhead
  4. Dwelded on both sides of the bulkhead

Correct answer: A) installed with watertight stuffing tubes