SeaQuiz

The first step when resetting the slide valves on a duplex reciprocating pump is to __________.

  1. Aposition the steam pistons on 3/4 stroke
  2. Bensure the balance piston is on the downstroke
  3. Cplace the steam pistons in the mid stroke position ✓
  4. Dmeasure the present port openings to ensure reassembly will be the same

Correct answer: C) place the steam pistons in the mid stroke position

USCG question bank (2008) · Engineering General Subjects – Question Bank Book 11 · pass mark 70%