When replacing a gasket in a six-bolt flanged joint, in what order should the bolts be tightened?

  1. AEach bolt should be installed and tightened in consecutive order in the clockwise direction.
  2. BEach bolt should be installed and tightened in consecutive order in the counterclockwise direction.
  3. CInstall and tighten bolts 1, 3, 4, 2, 5, and 6, in that order.
  4. DInstall and tighten bolts in pairs which are opposite each other in the flange (1-4, 2-5, and 3-6). ✓

Correct answer: D) Install and tighten bolts in pairs which are opposite each other in the flange (1-4, 2-5, and 3-6).

USCG question bank (2008) · Engineering General Subjects – Question Bank Book 11 · pass mark 70%