If the fixed material discharge piping between the P-tank and the on-deck outlet of the supply boat becomes clogged and cannot be cleared using normal system air pressure, the __________.

  1. Apiping must be flushed with water ✓
  2. Bair should be directed through the jet air line
  3. Cair pressure should be increased beyond the safety valve
  4. Dpiping must be disassembled and cleaned by hand

Correct answer: A) piping must be flushed with water