If at 75% load of two generators running in parallel, one of them shuts down, what emergency action will we take?

  1. ADisconnect of all non-essential consumers from the buses of the main switchboard. ✓
  2. BStart and turn on emergency generator.
  3. CRestart the disconnected generator.
  4. DCheck the main circuit breaker of the disconnected generator.

Correct answer: A) Disconnect of all non-essential consumers from the buses of the main switchboard.