When preparing the main switchboard to receive electric power, which action wil we take first?
- ACheck with a mega-ohmmeter the condition of the board insulation.
- BCarry out an external inspection of the main switchboard to ensure that there are no tools or object left on its current-conducting parts.
- CCheck for the absence of voltage in the main switchboard buses. ✓
- DCheck that air circuit breakers or other switching devices are not switched on.
Correct answer: C) Check for the absence of voltage in the main switchboard buses.