When preparing the main switchboard to receive electric power, which action wil we take first?

  1. ACheck with a mega-ohmmeter the condition of the board insulation.
  2. BCarry out an external inspection of the main switchboard to ensure that there are no tools or object left on its current-conducting parts.
  3. CCheck for the absence of voltage in the main switchboard buses. ✓
  4. DCheck that air circuit breakers or other switching devices are not switched on.

Correct answer: C) Check for the absence of voltage in the main switchboard buses.