Before measuring insulation with a megohmmeter, the windings of large electrical machines should be grounded for about 15 minutes before the start of the measurement because:
- AIt is possible to damage the insulation.
- BIt is possible that the insulation is wet.
- CThe armature windings will have a number of leakages.
- DLarge machines can potentially build up static electricity. ✓
Correct answer: D) Large machines can potentially build up static electricity.