While on an ocean tow, the COASTAL DRILLER is threatened with the approach of a severe storm. Including the time required to place the generators on-line, the approximate time required to lower the legs from a TOC (tip-of-can) position of 12.38 feet to 60.5 feet is __________.
- A8 minutes
- B32 minutes
- C40 minutes
- D47 minutes ✓
Correct answer: D) 47 minutes