Deck foam systems, designed to protect cargo areas on tank vessels built after January 1, 1975, must have a supply of foam-producing material to operate the system at its designed rate of foam production for __________.

  1. A15 minutes without recharging
  2. B20 minutes without recharging ✓
  3. C25 minutes without recharging
  4. D30 minutes without recharging

Correct answer: B) 20 minutes without recharging

USCG question bank (2008) · Deck Safety – Question Bank Book 4 · pass mark 70%