When would a jack-up drilling rig be considered "underway" under the International Rules of the Road?
- AWhen it is being towed to a new location ✓
- BWhen it is elevated and taking on preload
- CWhen it is elevated and engaged in drilling
- DWhen it is moored to a dock in the shipyard
Correct answer: A) When it is being towed to a new location