For planning purposes, the time required to place the DEEP DRILLER at survival draft from the drilling mode to counter heavy weather is __________. A2 hoursB4 hoursC6 hours ✓D8 hours Correct answer: C) 6 hours USCG question bank (2008) · Deck Safety – Question Bank Book 4 · pass mark 70%