After completing an IOPP certificate survey under Coast Guard Regulations (33 CFR Part 151), no significant change may be made in the construction, equipment, fittings, arrangements, or materials covered by the survey without the sanction of the _________.

  1. AState Water Management Authority
  2. BEnvironmental Pollution Agency
  3. CUSCG. Officer in Charge of Marine Inspection ✓
  4. DMarine Pollution Investigatory Board

Correct answer: C) USCG. Officer in Charge of Marine Inspection