While in a foreign port, burning and welding repairs are to be carried out on a section of heating coil located in a tank having last contained a grade "D" product. Which of the following procedures should be followed when a certified marine chemist is not available?

  1. AIt is solely the chief engineer's responsibility to ensure all safety precautions are observed, and all entries are to be made in the engine room log.
  2. BThe repair work cannot be done at this time due to the lack of the chemist's certificate.
  3. CPrior to any hot work, an inspection must be made by the senior officer present, and an entry made in the official logbook. ✓
  4. DRepairs should proceed as scheduled since a chemist's certificate is not required for that type of work.

Correct answer: C) Prior to any hot work, an inspection must be made by the senior officer present, and an entry made in the official logbook.

USCG question bank (2008) · Engineering Safety – Question Bank Book 15 · pass mark 70%

← PreviousNext →
Take the full practice test: Engineering Safety – Question Bank Book 15 →Free USCG practice test with the real pass mark, no sign-up

More questions from this module

Question list: Engineering Safety – Question Bank Book 15 (BK15)