According to Coast Guard regulations, keel cooler installations are __________.

  1. Arequired on all vessels of less than 150 gross tons
  2. Bto be made between the bilge keel and the keel
  3. Cto be provided with shutoff or isolation valves except when installed forward of the collision bulkhead ✓
  4. Dto be provided with expansion tanks, which must be located below the load line to provide positive cooling water flow

Correct answer: C) to be provided with shutoff or isolation valves except when installed forward of the collision bulkhead

USCG question bank (2008) · Motor Plants and Auxiliary Boilers – Question Bank Book 14 · pass mark 70%