Coast Guard Regulation (46 CFR) requires that after undergoing extensive repairs, an auxiliary boiler, with a maximum allowable working pressure of 60 psig (411.89 kPa), should be hydrostatically tested at a pressure of __________.
- A75 psig (514.86 kPa)
- B80 psig (549.18 kPa)
- C90 psig (617.83 kPa) ✓
- D120 psig (823.77 kPa)
Correct answer: C) 90 psig (617.83 kPa)