Air receivers installed in starting air systems are to be __________.

  1. Acylindrical in shape with service connections located at the top and bottom
  2. Bopened and made available for inspection during biannual inspections
  3. Cprovided with automatic drain traps for the removal of moisture
  4. Dso installed as to make the drain connections effective under extreme conditions of trim ✓

Correct answer: D) so installed as to make the drain connections effective under extreme conditions of trim

USCG question bank (2008) · Motor Plants and Auxiliary Boilers – Question Bank Book 14 · pass mark 70%