Which of the following statements is correct for the design and installation of diesel engine cooling water systems?

  1. AAn alarm device with audible and visible signals is required for all cooling water systems.
  2. BPropulsion engines with bores over 200 mm are to be fitted with cooling water thermometers at each cylinder.
  3. CEach totally enclosed cooling system shall be provided with a suitable head tank.
  4. DDrain cocks are to be provided at the lowest points of all cylinder water jackets. ✓

Correct answer: D) Drain cocks are to be provided at the lowest points of all cylinder water jackets.

USCG question bank (2008) · Motor Plants and Auxiliary Boilers – Question Bank Book 14 · pass mark 70%