SeaQuiz

The principal purpose of refractory and insulation installed in the firebox of an auxiliary boiler is to __________.

  1. Aprevent slag accumulation on the corbels
  2. Bprotect the inner casing and reduce heat loss ✓
  3. Cdirect the force draft into the space between the inner and outer casings, to maintain a pressure seal
  4. Dprevent flame impingement on the generating tube bank

Correct answer: B) protect the inner casing and reduce heat loss

USCG question bank (2008) · Motor Plants and Auxiliary Boilers – Question Bank Book 14 · pass mark 70%