Bottom blow valves are installed on auxiliary water-tube boilers to __________.

  1. Acompletely drain the boiler in an emergency
  2. Bprevent sludge from forming in the steam drum
  3. Cremove floating impurities from the boiler water surface
  4. Dremove settled solids from the water drum ✓

Correct answer: D) remove settled solids from the water drum

USCG question bank (2008) · Motor Plants and Auxiliary Boilers – Question Bank Book 14 · pass mark 70%