When an auxiliary boiler is secured and you expect to relight the unit within six hours, you should __________.

  1. Amaintain a head of steam not less than 10 psig ✓
  2. Bcompletely fill the boiler with feed water
  3. Cflush the boiler and close the waterside airtight
  4. Dmaintain steam pressure 10 psig below normal boiler load

Correct answer: A) maintain a head of steam not less than 10 psig

USCG question bank (2008) · Motor Plants and Auxiliary Boilers – Question Bank Book 14 · pass mark 70%