Where is a fusible plug installed on a Scotch or auxiliary boiler?
- AAt the shell approximately 1 1/2 inches (3.8 cm) below the normal waterline.
- BAt or near the center of the crown sheet of the combustion chamber. ✓
- CIn the furnace approximately 1 1/2 inches (3.8 cm) below the normal waterline.
- DIn the furnace not more than 1 inch (2.54 cm) below the lowest permissible water level.
Correct answer: B) At or near the center of the crown sheet of the combustion chamber.