Which of the routine maintenance procedures listed is required for starting air receivers?

  1. AFrequent draining of accumulated moisture. ✓
  2. BFrequent testing of relief valves.
  3. CA close watch on temperature to prevent fluctuations in pressure.
  4. DFrequent cleaning to remove oil and foreign matter.

Correct answer: A) Frequent draining of accumulated moisture.

USCG question bank (2008) · Motor Plants and Auxiliary Boilers – Question Bank Book 14 · pass mark 70%