In readying an auxiliary water-tube boiler for a routine hydrostatic test, which of the following procedures should be undertaken prior to filling the boiler with fresh water?
- AThe safety valve escape piping should be disconnected from the valve body and a blank inserted.
- BThe boiler vent valves should be opened. ✓
- CAll handhole/manhole covers should be tightened up as much as possible to preclude any leaks.
- DAll of the above.
Correct answer: B) The boiler vent valves should be opened.