In readying an auxiliary water-tube boiler for a routine hydrostatic test, which of the following procedures should be undertaken prior to filling the boiler with fresh water?

  1. AThe safety valve escape piping should be disconnected from the valve body and a blank inserted.
  2. BThe boiler vent valves should be opened. ✓
  3. CAll handhole/manhole covers should be tightened up as much as possible to preclude any leaks.
  4. DAll of the above.

Correct answer: B) The boiler vent valves should be opened.

USCG question bank (2008) · Motor Plants and Auxiliary Boilers – Question Bank Book 14 · pass mark 70%