While standing watch underway, if the brine level of a low pressure distilling plant is above the sight glass, which action should be taken?
- ADo nothing as this is the normal operating level.
- BReduce the feed rate and check the brine eductor system. ✓
- CThe brine overflow weir should be raised to allow greater outflow.
- DThe brine section should be drained down a minimum of 6 inches below the seawater heater bundle.
Correct answer: B) Reduce the feed rate and check the brine eductor system.