According to Coast Guard Regulations (46 CFR), the studs and bolts on marine boiler mountings must be removed for examination at least every __________.
A3 years
B4 years
C5 years
D10 years ✓
Correct answer: D) 10 years
USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%