Prior to relieving the watch you should first check the fire room status by verifying the boiler water level and __________.

  1. Asteam atomization pressure to the mechanical atomizers
  2. Bfuel pressure to the burners ✓
  3. Cfuel oil viscosity
  4. Dwater drum level

Correct answer: B) fuel pressure to the burners

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%