When starting a turbo generator in an automated plant, you must provide lube oil pressure to the unit by means of __________.

  1. Aa line from the other generator
  2. Ba line from the gravity tank
  3. Cthe main lube oil pump
  4. Dthe hand operated or auxiliary lube oil pump ✓

Correct answer: D) the hand operated or auxiliary lube oil pump

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%