A boiler is to be secured in port. After the burners have been secured, the forced draft fan and air registers should be secured __________.

  1. Aimmediately after carrying out the former procedures
  2. Bafter any oil on the furnace floor has been burned off and cleared of combustion gases ✓
  3. Cafter 30 minutes has elapsed, after carrying out these procedures
  4. Dafter at least 1 hour has elapsed, after carrying out these securing procedures

Correct answer: B) after any oil on the furnace floor has been burned off and cleared of combustion gases