Prior to lighting a burner in a cold boiler, you should __________.

  1. Aclose the superheater vent
  2. Bblow down the mud drum
  3. Copen the surface blow valve
  4. Dthoroughly purge the furnace ✓

Correct answer: D) thoroughly purge the furnace