SeaQuiz

When water washing a boiler, the proper sequence for washing the sections should be the __________.

  1. Agenerating tubes, superheater, and then economizer
  2. Bsuperheater, economizer, and then generating tubes
  3. Cscreen tubes, generating tubes, and then superheater
  4. Deconomizer, superheater, generating, and then screen tubes ✓

Correct answer: D) economizer, superheater, generating, and then screen tubes

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%