If an operating propulsion unit requires excessive quantities of gland sealing steam, you should suspect a __________.

  1. Avacuum leak in the condenser shell
  2. Bflooded main condenser hotwell
  3. Cworn or damaged labyrinth packing ✓
  4. Drestriction in the gland leak off piping

Correct answer: C) worn or damaged labyrinth packing

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%