SeaQuiz

To prevent damage to the turning gear mechanism, which of the following procedures must be carried out before the turning gear is engaged?

  1. AThe brake on the first reduction worm shaft must be set.
  2. BThe propeller shaft must be stopped and held stationary until the clutch is engaged. ✓
  3. CThe engine order telegraph must be on 'stop'.
  4. DThe speed of the astern turbine must be reduced.

Correct answer: B) The propeller shaft must be stopped and held stationary until the clutch is engaged.

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%

← PreviousNext →
Take the full practice test: Steam Plants – Question Bank Book 13 →Free USCG practice test with the real pass mark, no sign-up

More questions from this module

Question list: Steam Plants – Question Bank Book 13 (BK13)