When a boiler economizer is fitted with a valved bypass, Coast Guard Regulations (46 CFR) require which of the following devices to be installed?
- AA sentinel valve is to be fitted on the superheater outlet.
- BA stop check valve is to be located at the economizer outlet. ✓
- CA stop check valve is to be located at the economizer inlet.
- DAn emergency drain line must be provided to the reserve feed tank.
Correct answer: B) A stop check valve is to be located at the economizer outlet.