SeaQuiz

As a result of a serious mechanical malfunction in one of the ship's service generators operating in parallel, you must secure that generator. In order to prevent a possible overload to the remaining generator, which of the following sequential courses of action should be taken?

  1. ATrip the malfunctioning generator's circuit breaker and prime mover throttle trip.
  2. BTrip all non-vital distribution feeder circuit breakers, remove the remaining load on the malfunctioning generator and trip its circuit breaker and then the prime mover throttle trip. ✓
  3. CTrip the malfunctioning generator's circuit breaker and distribution feeder circuit breakers.
  4. DTrip all non-vital distribution feeder circuit breakers, the malfunctioning prime mover turbine throttle trip, and the generator circuit breaker.

Correct answer: B) Trip all non-vital distribution feeder circuit breakers, remove the remaining load on the malfunctioning generator and trip its circuit breaker and then the prime mover throttle trip.

USCG question bank (2008) · Electricity – Question Bank Book 12 · pass mark 70%

← PreviousNext →
Take the full practice test: Electricity – Question Bank Book 12 →Free USCG practice test with the real pass mark, no sign-up

More questions from this module

Question list: Electricity – Question Bank Book 12 (BK12)