Before testing insulation with a megohmmeter, the windings of large machines should be grounded for about 15 minutes just prior to the test as the __________.
- Ainsulation may be damaged
- Binsulation may be covered with moisture
- Carmature windings will have a greater number of leakage paths
- Dlarger machines may acquire a charge of static electricity during operation ✓
Correct answer: D) larger machines may acquire a charge of static electricity during operation