Coast Guard Regulations (46 CFR) require that each alternating current generator arranged for parallel operation shall be provided with __________.

  1. Amore than one means of excitation
  2. Bindividual circuit fuses
  3. Ca high back-pressure trip
  4. Da reverse-power trip ✓

Correct answer: D) a reverse-power trip

USCG question bank (2008) · Electricity – Question Bank Book 12 · pass mark 70%