In preparing to take insulation resistance readings on a main generator, the windings should be grounded for about 15 minutes prior to the test to __________.

  1. Aallow accurate zeroing of the meter
  2. Bhelp the windings to cool to ambient temperature
  3. Crelease any residual capacitive charge from the windings ✓
  4. Dhelp the windings to cool to the same temperature as the ground test connection

Correct answer: C) release any residual capacitive charge from the windings

USCG question bank (2008) · Electricity – Question Bank Book 12 · pass mark 70%