When securing a distillate pump on a low pressure fresh water evaporator, which of the listed steps should be carried out FIRST?

  1. AStop the pump.
  2. BClose the pressure gage valves.
  3. CTrip the three-way solenoid dump valve. ✓
  4. DClose the sealing line valves to the pump.

Correct answer: C) Trip the three-way solenoid dump valve.