SeaQuiz

Which of the following actions should be taken FIRST if a bilge well of a multiple suction bilge system is unable to be pumped out?

  1. AOpen the bilge pump for inspection.
  2. BRemove each of the suction manifold valves.
  3. CRemove only the suction manifold valve to the affected bilge well.
  4. DAttempt to pump out another bilge well to determine if the entire system is affected. ✓

Correct answer: D) Attempt to pump out another bilge well to determine if the entire system is affected.

USCG question bank (2008) · Engineering General Subjects – Question Bank Book 11 · pass mark 70%