Which of the following intervals do Coast Guard Regulations (46 CFR) require the remote cutout for the fuel oil service pumps to be tested?
- APrior to each sailing
- BOnce each month
- CAt each fire and boat drill
- DAt each inspection for certification ✓
Correct answer: D) At each inspection for certification