SeaQuiz

An unloader is installed on an air compressor to __________.

  1. Abypass the high pressure stage to the low pressure stage on 100% of the air compressors in service
  2. Bprevent excessive interstage pressure buildup
  3. Ccontrol compressor discharge pressure
  4. Dremove all but the frictional load during starting ✓

Correct answer: D) remove all but the frictional load during starting

USCG question bank (2008) · Engineering General Subjects – Question Bank Book 11 · pass mark 70%