Dry bulk material transfer to an offshore drilling rig has just begun when you discover air leaks at the P-tank manhole cover. You must __________.
- Acomplete the discharge before attempting any repairs
- Bde-pressurize the tank, inspect, clean and reseat the gasket ✓
- Creduce the P-tank pressure to 25-30 psi to complete the transfer
- Dplace a burlap bag around the leaking manhole flange
Correct answer: B) de-pressurize the tank, inspect, clean and reseat the gasket