SeaQuiz

Dry bulk material transfer to an offshore drilling rig has just begun when you discover air leaks at the P-tank manhole cover. You must __________.

  1. Acomplete the discharge before attempting any repairs
  2. Bde-pressurize the tank, inspect, clean and reseat the gasket ✓
  3. Creduce the P-tank pressure to 25-30 psi to complete the transfer
  4. Dplace a burlap bag around the leaking manhole flange

Correct answer: B) de-pressurize the tank, inspect, clean and reseat the gasket

USCG question bank (2008) · Engineering General Subjects – Question Bank Book 11 · pass mark 70%