Which statement about calibrating a newly installed thermostatic expansion valve is correct?

  1. AThe procedure requires a refrigeration wrench and a digital thermometer to measure box temperature.
  2. BNo special tools are required as long as the solid state circuit control panels are functioning properly.
  3. CThis procedure is done at the factory with tools not available to a mariner.
  4. DAn accurate thermometer and suction pressure gage are essential to this process. ✓

Correct answer: D) An accurate thermometer and suction pressure gage are essential to this process.