You discover an air leak at the manhole cover shortly after pressurizing a P-tank. You must __________.
- Areduce the P-tank pressure to 25-30 psi to complete the dry material transfer
- Bincrease the P-tank pressure to the unloading valve setting to force the manhole cover to seat itself
- Ccomplete the dry material discharge before attempting any repairs
- Ddepressurize the tank, replace the gasket, then tighten the bolts securing the hatch cover ✓
Correct answer: D) depressurize the tank, replace the gasket, then tighten the bolts securing the hatch cover